Salhiyat Al Abed Bridge
Work Type
  • Underpass Construction
  • The project consisted of two direction underpasses with 3 lanes for each Side.
  • Retaining   Walls, Electrical works, pavements & Guard rails.
  • The project included the excavation works, Reinforcements according to design drawings, expansion Joints covers, water proofing and hand Rails protection.
  • 4,000 m3 Concrete
  • 600 tons of Steel Reinforcement
  • Tunnel Built up a rea 200 m2
  • Tunnel Long:  20 LM
  • Fast Track Project (7 months)
  • Detouring works
Locations:
Amman, Jordan
Clients:
Greater Amman Municipality
Start Date:
01-05-2007
Finish Date:
01-12-2007