Sahab Bridge
Work Type
  • Underpass Construction
  • The project consisted of two direction underpasses with 3 lanes for each Side.
  • Retaining   Walls, Electrical works, pavements & Guard rai ls.
  • The project included the excavation works, Reinforcements according to design drawings. Load bearings pads, expansion Joints covers, water proofing and hand Rails protection.
  • 4,000 m3 Concrete
  • 350 tons of Steel Reinforcement
  •  Tunnel Built up a rea 360 m2
  • Tunnel Long:  100 LM including Wing Walls
  •  Fast Track Project (5 months)
  • Detouring works
  • Post tensioning slab
Locations:
Amman, Jordan
Clients:
Greater Amman Municipality
Start Date:
01-10-2008
Finish Date:
01-02-2009