Fannoun Underpass
Location
Amman, Jordan
Client
Greater Amman Municipality
time line
1/2/2009 - 1/6/2009
scope of work
The project consisted of construction Tunnel and three bays underpass and three lane for each side, retaining walls, electrical works, pavement with guard rails, including excavation & shoring works.
the Works include 3500m3 of concrete and 300 ton of reinforcement steel, with a total area of tunnel 270m2 and tunnel long 30m.
It’s fast track project (4 Months)